ROAD WORK UPDATE
ROAD WORK UPDATE The pavement recycling on Wisner, Billings and Springer were completed last week. From this point, the recycled base on each street needs some time to [...]
ROAD WORK UPDATE The pavement recycling on Wisner, Billings and Springer were completed last week. From this point, the recycled base on each street needs some time to [...]
The contractor will complete the recycling phase of Billings Road today and, weather permitting, begin on Springer tomorrow (August 3).
Tonight’s Special Meeting of City Council will be held at 6:00 pm in Council Chambers. The meeting is open to the public and is also available via Zoom [...]
Wonderstruck in Cleveland (but being hosted in Kirtland) - THIS WEEKEND See below for more information regarding Wonderstruck. A special thanks to our own Police and Fire Departments [...]
ROAD WORK UPDATE Work on Billings Road will begin tomorrow (Saturday, July 24). This phase is expected to take about two weeks. As always - all work is [...]
Pavement Rehabilitation began yesterday on Wisner Road. The contracted process described below will take place over 30-45 days for each road. 1. Recycle the pavement 2. Proof roll [...]
ROAD WORK - NOTICE TO RESIDENTS CITY OF KIRTLAND Billings, Springer – Springer Ct., Wisner 2021 PAVEMENT REHABILITATION WORK TO COMMENCE ON OR ABOUT JULY 19, 2021 THE [...]
Tonight’s City Council meeting is open to the public, both in person and via Zoom (see link below). Please note that the public hearing will conclude tonight’s Council [...]
The Lake County General Health Division will be spraying for mosquitos tomorrow (Thursday, July 8).
I can officially say we are off to a great summer here in Kirtland. With neighbors helping neighbors, new civic partnerships, a community survey, exciting outdoor events, and [...]