SR306 Bridge Work
The SR306 Bridge is scheduled to be closed beginning March 18.
Detours will be posted this week.
The detour route for northbound traffic on SR306 will be SR615 to I-90.
During Phase 1 of the work, eastbound traffic on Markell Road at SR306 will be right-turn only.
This project is scheduled to be completed by late October 2024.
Old Town Sewers
Work on this project is expected to begin on 3/12/24. Proposed schedule for the work as follows.
Main line sewer installation:
Maple Street: March 12 – April 8
Coudry Street: April 9 – April 22
Fairview Ave: April 23 – May 20
Elm Street: May 21 – June 5
Joseph Street: June 6 – July 8
Service Laterals: July 9 – August 28
Testing, restoration & pavement repair: 8/29 – 11/16