These weekly updates will include both work completed as well as next steps. Work is scheduled week to week and is contingent on weather. All road work is expected to be completed by late October/early November.
City of Kirtland 2021 Road Paving & Maintenance Update
Week ending October 22, 2021
Completed Work:
Pavement Recycling / Proof roll to identify needed base repairs
Billings
Wisner
Springer Drive
Springer Court
Beechwood
Double Chip Seal
Wisner
North/South Locust
Charlesderry
Glen Park
North Star
Full Depth Pavement Repairs and Intermediate Asphalt
Springer Drive
Springer Court
Full Depth Pavement Repairs
Beechwood and Oakwood
Intermediate Asphalt Surface
Billings
Beechwood and Oakwood
Sweep and mastic surface sealant
North/South Locust
Temporary Pavement Markings
Billings
Crack Sealing
Tibbets
Woodlake
Installation of base repairs, asphalt surface, berms, and drainage
Springer Drive
Springer Court
Installation of berms and drainage
Billings
Next Steps:
Installation of berms, installation of asphalt surface and final striping
Billings
Springer, Springer Ct.
Beechwood and Oakwood
Berming and drainage
Beechwood and Oakwood
Crack sealing
Euclid Chardon (in progress)
Kirtland Lakes Blvd.
Asphalt rejuvenator
Wrenwood
Singlefoot Trail
Arborhurst
City wide pavement striping, crack seal, and asphalt patch repair will continue.