These weekly updates will include both work completed as well as next steps. Work is scheduled week to week and is contingent on weather. All road work is expected to be completed by late October/early November.
City of Kirtland 2021 Road Paving & Maintenance Update
Week of September 14, 2021
Completed Work:
Pavement Recycling / Proof roll to identify needed base repairs
Billings
Wisner
Springer Drive
Springer Court
Beechwood
Double Chip Seal
Wisner
North/South Locust
Charlesderry
Glen Park
North Star
Full Depth Pavement Repairs and Intermediate Asphalt
Springer Drive
Springer Court
Next Steps:
Full Depth Pavement Repairs
Beechwood and Oakwood (should be completed early next week)
Intermediate Asphalt Surface
Billings (should be completed by end of week)
Installation of berms and drainage
Billings
Installation of base repairs, asphalt surface, berms, and drainage
Springer Drive
Springer Court
Asphalt resurfacing, berming, and drainage
Beechwood and Oakwood
Sweep and mastic surface sealant
Wisner
North/South Locust
Charlesderry
Glen Park
North Star
Crack sealing
Euclid Chardon
Tibbets
Kirtland Lakes Blvd.
Asphalt rejuvenator
Wrenwood
Singlefoot Trail
Arborhurst
City wide pavement striping, crack seal, and asphalt patch repair will continue.